Project Helios

Project Helios in Hokkaido is one of Japan’s early large-scale battery energy storage system (BESS) projects to begin commercial operation, with an output of 50 MW and an energy capacity of 104 MWh.
Location:Shinkawa, Hokkaido
Capacity :50 MW / 104 MWh
Operating life :~25 years
Technology :Lithium Iron Phosphate (LFP)
Status : Commercial Operations
COD:December 2025

Overview

Project Helios is one of Japan’s early utility-scale battery energy storage system (BESS) developments. The project has been operating in Fukagawa, Hokkaido since December 2025. It was developed by Manoa Energy, Brawn Energy’s predecessor company, and later transferred to HDRE. Helios is an example that demonstrates Brawn Energy’s end-to-end development capabilities.

This project was acquired prior to the RTB (Ready-to-Build) stage and was developed through the following milestones:

  • Securing construction permits and grid interconnection approval
  • Executing the EPC services contract and procuring the full BESS system
  • Project management, including delivery and installation of battery units, in coordination with the utility, nearby infrastructure projects, the local community, and key stakeholders
  • Grid impact study and permitting for the private transmission line

Community engagement

Building relationships with local communities plays a key role in how we develop projects. At Helios, through dialogue with local residents, we responded to concerns raised during the development process by installing lighting at a nearby public bus stop.

Manoa Energy’s role

Beyond development, Brawn also served as the construction manager through commercial operations, coordinating with the utility, nearby infrastructure projects, and key stakeholders.

Milestones

December 2022:Project acquired
November 2023:Technical design completed
January 2024:EPC contract executed
April 2024:Construction started
October 2024:Foundation works scheduled for completion
March 2025:60% stake transferred
April 2025:BESS delivery completed
June 2025:Substation installed
July 2025:Grid interconnection
December 2025:Commercial operation date (COD)
December 2025:Transition to operations phase

Gallery

Our Projects

Project Maibara

Capacity: 50 MW
Location : Maibara City, Shiga Prefecture, Kansai
Technology : Lithium-Ion Battery
Status : Under Development

Project Mooka

Capacity: 50 MW
Location : Mooka City, Tochigi Prefecture, TEPCO
Technology : Lithium-Ion Battery
Status : Under Development